A5 Re-surfacing works
A5 resurfacing works
I’m writing to inform you of some upcoming essential maintenance work on the A5 between Tove roundabout and Gibbet Island. As part of this work, we’ll carry out resurfacing, renewal of road markings and replacing road studs to provide a smoother, safer carriageway for road users.
When will this work take place?
We’ll be working overnight, from 21 October 2024 to 1 November 2024, 8pm to 6am Monday to Friday.
To complete our work safely, we’ll install full overnight closures of the A5 between Crick and Shawell (3 nights), followed by Weedon Bec to Crick (2 nights) and a final phase from Tove/Towcester roundabout to Weedon Bec. (2 nights).
What does this mean for you?
During the closures, the following fully signed diversions will be in place.
Crick to Shawell – motorway traffic
Crick to Shawell – non motorway traffic
Weedon Bec to Crick – motorway traffic